We’ve gotten news that Kent Ridge is soon to be ready. We are talking about in a week or so. Meanwhile, some updates on the North Shore rides available @ http://kentridge.eaglet.org

faraway so close

We are almost done with the North shore section. is rainy and wet, equipment rusting, nailing and finishing getting worse. Alvin Jeff and me take our work on existing fallen log. Seriously inexperience on log work we are. can’t seems to secure the pieces together to get a stiff structure with those big logs. After ...

the banked roller

With the first ramp built leading to nowhere since day one, we decided to give this best line the fastest and most technical bridge we ever built. A banked roller that twist and bank 3 times in a space of 4metres. Liyana and Alvin got things started with the nailing while I do most of ...

layout and planking the floor

with the wooden berm stopping at a box T-junction, Jeff started the connecting 1.5metres long floor section, so to finish the loop for the roller coaster straight and the beginner loop. The fast roller section is also layout. We can start building this technical banked roller, the most technical till date tomorrow. I always wanted ...

the beginner section

another start early end late day. With the beginner ‘low’ North Shore section lay out by Jeff a day earlier, Me and Alvin took 5mins to visualized and then jump straight to build the tall end of the beginner loop. It took us the whole morning to progress 5 metres, but we managed to get ...

here comes the power tools

With much of the wooden structure hand build with saw and hammer. We took a jigsaw and power drill to see what we can build out of it. Nik and I meet for the afternoon. Our task today involved doing up a small 2metres long section, connecting a new entry ramp to the straight roller ...

Completing the details

It’s a full day work at Kent Ridge. Alvin and Liyana met up with me at the North Shore section early. Apparently with the help of Liyana, he got the roller coaster straight started yesterday. Leaving today with completing the V ramps for the ‘Roller Jump’. With the recent thunderstorm, we are lucky to have ...

the ‘New Section’

Much as we are trying to make sure everyone get updated with info, we got to zip this until this New Stuff is almost ready. And yes we are there. We just received the new batch of woods for the stringers, and trail construction kicks in again officially today. We finished the Y-junction today, with ...

waking up just as september ends

Alright, is about 2 months since we’ve done real work on the trail. The past 2months were spent waiting for the rain and sediment to weather the trail, giving a good foundation before the heavy riding expected. While Alvin and gang worked the new long downhill section with proper anti-erosion barrier, I spent my time ...

a typical trail building day

Finally injury caught up with me (non trail or bike related), While Alvin and Liyana work the day with the 3 workers, completing and bench cutting sections of the uphill section of the fern hill, I took the time off to test out our Virtual Maps sponsored GPS tracking units so to mark the trails. ...