The Valley before Construction
the February sun really flaunt its ray the whole afternoon.
We took the trail out of the valley towards Ziggurat and build a V-section switchback upwards, taking the opportunity to train the bunch of construction crew on build techniques.
The short 30metres section should take a total of a day with the help of excavator.

Initial build of the rolling crown switchback.

after 3 hours of rock moving and excavation, the foundation of the switchback is ready for the next phase tomorrow.
meanwhile at the BMX area, the area is flatten and graded for drainage.

desert storm