The objective of the day is to complete the prototype of the rock garden. with a reduced workforce of just 4 worker, 2 operators and… Read More »Pave!
The objective of the day is to complete the prototype of the rock garden. with a reduced workforce of just 4 worker, 2 operators and… Read More »Pave!
we attempted unsupervised trail building the past 2 days, in hope certain simpler task can be done without close supervision. the end results is about 85% satisfactory… Read More »The new horizon hill
This is going to be the toughest part of the build, some long section of rock armor work to be worked on for the next… Read More »the hardest part
the continuous climb requires days of work to get it right. the crew is now pretty well trained in shaping the reversal, dips and climbs.… Read More »the long climb
We’ve a big team for the build today and as usual it’s best to split the team to various work area to be safe and… Read More »Inslope Turn for a change
the best looking if not the best ride thus far, with a full day earth moving, earth shaping and compacting. we’ve a nice 6 inslope… Read More »Flume Ride
The momentum is picking up over the past few days. We are officially into Day 4 of the mountain biking trail building for Tampines Bike… Read More »in need of flow testing
with about 10 workers available for the day. Jason and I split the work team so to work on two areas at the same time.… Read More »Is a flume ride
the February sun really flaunt its ray the whole afternoon. We took the trail out of the valley towards Ziggurat and build a V-section… Read More »Zig Climb
The work started at the ‘Valley’ with drainage and foilage clearance work today. The exploratory dig reveals we needed more machinery for this task especially… Read More »the mice drop